"Building an offshore drilling rig usually takes three years. It may be hard to believe, but the delivery of one of our rigs was delayed for almost a year because of our lack of experience."
Liu Yanjia, vice-president of CIMC Raffles, says it usually takes 30 months for a Singapore company to finish a drilling platform, but because of a lack of management experience in his company, it needs 35 months to build something comparable. "A longer production process means higher production costs," he says.
Given buyers' concerns on delivery reliability, China remains a distant No 3 in terms of offshore rig-building market share, a report from Reuters says. In the first half of last year China secured just three orders out of the 29 placed during the period, against 11 for South Korea and six for Singapore, data from Credit Suisse shows.
However, Gao says his company and its Chinese peers can overcome that shortage with their growing experience in building rigs. Industry insiders agree, saying the technology gap between Chinese offshore rig builders and their rivals can be closed in a relatively short time. What is hurting at the moment is the gap between management and operational expertise.
Gao says that construction of one of the rigs CIMC Raffles is building is ahead of schedule. With an increasing number of orders resulting from the boom in offshore oil exploration, the company will soon gain more experience, he says.
The company, which delivered three rigs last year, has three incoming orders and is now building a total of seven, he says.
Despite the years of development and the achievements the company has made, Gao acknowledges that it still has a long way to go.